Waste heat boiler with ip-tube for the University Hospital Bonn
Engie Deutschland GmbH | Bonn
At the University Hospital Bonn site, the use of a waste heat steam boiler downstream of three gas engines in CHP was implemented to increase the overall efficiency of the plant.
Project Highlights
3.3 t/h steam at 13 bar from 3 MWM gas engines
Compact ip-tube design for extremely confined spaces
Complete installation including piping and on-site commissioning
Initial Situation
- At the University Hospital Bonn site, the use of a waste heat steam boiler downstream of three gas engines in CHP was planned to significantly increase the overall efficiency of the plant.
- Due to extremely confined spaces, only a compact boiler design using structural tubes (ip-tube) was feasible.
The Solution from SCHNEIDER-KESSEL BERLIN®
An AHK-ip 3200/13 waste heat boiler with ip-tube structural tubes was designed, manufactured, and delivered, connected to three MWM gas engines (type TCG 2020V20). The scope of delivery includes bypass control dampers, complete boiler equipment, and control technology for 72 h BoB. SCHNEIDER also performed the complete installation, piping connection, and commissioning of the entire system on site.
Our Services
- Design, manufacture, and delivery of an AHK-ip 3200/13 waste heat boiler with ip-tube structural tubes, connection to 3 gas engines (MWM TCG 2020V20)
- Delivery including bypass control dampers, boiler equipment, and control technology (72 h BoB)
- Installation, piping connection, and commissioning of the entire system on site
Inspired by this solution?
Learn more about our waste heat boilers
Waste heat boiler
Our waste heat boilers use industrial exhaust heat to generate steam. Reduce your energy costs and CO₂ emissions.
Positive Customer Benefits and Added Value
- Significantly increased CHP efficiency through waste heat utilization downstream of all three gas engines
- Compact design through ip-tube technology even in extremely limited space
- Reliable steam supply for various hospital areas around the clock
- 72 h BoB for operator-friendly operation with minimal personnel requirements
- Turnkey solution including piping construction and commissioning
- Operational safety through reliable bypass control
- Made in Germany – quality for critical infrastructure
Speak to Our Experts
Whether you need a new system or want to optimize existing steam systems, we provide individual advice and find the right solution for your process.