Electric auxiliary steam generator for keeping a combined-cycle power plant warm

Energie und Wasser Potsdam GmbH | Potsdam

Energie und Wasser Potsdam GmbH operates the Potsdam Süd CHP plant as a combined-cycle power plant (CCPP). To supply the plant during shutdown periods with keep-warm steam and sealing steam for the steam turbine bearing seals, a reliable electric auxiliary steam generator was required.

Project Highlights

1,100 kg/h auxiliary steam at 10 bar for combined-cycle power plant

Sealing steam for steam turbine bearing seals

72 h BoB – fully autonomous operation without on-site personnel

Initial Situation

  • An electric auxiliary steam generator was to be installed at the Potsdam Süd combined-cycle power plant to provide keep-warm steam during shutdown periods.
  • In addition, sealing steam was to be supplied for the steam turbine bearing seals.

The Solution from SCHNEIDER-KESSEL BERLIN®

An electrode steam generator of type HDO-E 750/10 with a capacity of 1,100 kg/h (710 kW) at 10 bar was designed, manufactured and supplied. The scope of supply includes all valves and auxiliary equipment as well as the control and switchgear system for 72-hour unattended operation (BoB). SCHNEIDER provided complete installation services including positioning, installation, complete piping installation and commissioning.

Our Services

  • Engineering, manufacture and supply of an HDO-E 750/10 electrode steam generator (1,100 kg/h / 710 kW)
  • All valves, auxiliary equipment, and control and switchgear system for 72 h BoB
  • Complete installation services: positioning, installation, piping installation and commissioning

Inspired by this solution?

Learn more about our electric boilers

Electric steam boilers

Zero-emission steam generation using electric heating. Flexible and low-maintenance.
HDO-E | Freisteller | Elektrokessel | Produkt | Schneider-Kessel Berlin

Positive Customer Benefits and Added Value

  • Reliable keep-warm operation of the combined-cycle power plant in all shutdown phases
  • Protection of the steam turbines through continuous sealing steam supply to the bearing seals
  • Fully autonomous operation with 72 h BoB – no on-site personnel required
  • Rapid return to service of the power plant thanks to the system being kept warm at all times
  • Turnkey delivery including piping and commissioning
  • Durable resistance heating elements for low-maintenance operation
  • Made in Germany – reliability for critical energy infrastructure